ENGINEERING DESIGN PERFORMANCE
Active Project Portfolio
ANONYMIZED DEMO All names, codes, people, dates, and figures below are fictional.
AV-101Northpoint Process FacilityAT RISK
DRAWING PROGRESS72.4%PLAN 78%
MH UTILIZATION78%9,660 / 12,400 h
286Drawings12Overdue
AV-102Harborview Utilities UpgradeON TRACK
DRAWING PROGRESS88.3%PLAN 86%
MH UTILIZATION78%8,420 / 10,800 h
314Drawings4Overdue
AV-103Meridian Health CampusON TRACK
DRAWING PROGRESS64.8%PLAN 63%
MH UTILIZATION60%8,750 / 14,600 h
402Drawings3Overdue
AV-104Vertex Data InfrastructureON TRACK
DRAWING PROGRESS55.6%PLAN 56%
MH UTILIZATION53%4,860 / 9,200 h
220Drawings2Overdue
AV-105Summit Manufacturing HubAT RISK
DRAWING PROGRESS79.1%PLAN 84%
MH UTILIZATION85%11,210 / 13,200 h
356Drawings9Overdue
AV-106Blueleaf Consumer ProductsON TRACK
DRAWING PROGRESS51.3%PLAN 50%
MH UTILIZATION48%5,720 / 11,800 h
264Drawings1Overdue
Portfolio Progress
Man-Hours Utilization
69%
49,420 of 72,000 budget hours consumed.
Management Attention
- AV-101Schedule varianceHIGH
- AV-105Man-hour trendMEDIUM
- AV-102Approval cycleLOW